2022 Street Improvement Project
UPDATE 11/11/2022
All driveway repairs, landscape restoration and utility adjustments have been completed. Peter Baker & Son is planning to perform paving starting Monday, November 14 through Tuesday, November 15. No parking signs will be posted on Saturday to notify motorists of the pending schedule. Pavement striping will be scheduled accordingly based on the asphalt completion.
UPDATE 10/19/2022
Leveling binder (first) layer asphalt installation is scheduled for Thursday (10/20) and Friday (10/21). Finishing of concrete sidewalk/curb and temporary measures to ensure a safe and fun Trick or Treat Main Street are scheduled for the week of 10/24.
UPDATE 10/14/2022
Main Street (Garland Road to Il Route 176)
Milling is to commence Saturday, October 15 at 7:00 AM and will be completed by mid morning. Base preparation will be conducted early in the week with binder (first) layer asphalt installation scheduled for mid-week. Miscellaneous concrete repairs scheduled for the week of October 24th along with temporary measures to ensure a safe and fun Trick or Treat on Main Street.
UPDATE 10/4/2022
The attached project flyer provides a general overview of the anticipated schedule. Material availability has challenged the contractor’s ability to schedule some work at the speed they would prefer. Please know that the Village and Peter Baker & Son Co. are working closely to ensure the project is completed as quickly as possible with the limitations presented.
UPDATE 9/21/2022:
2022 Street Improvement Project
Main Street (Garland Road to Il Route 176)
What to Expect:
The contractor will begin saw cutting curbs and sidewalks the week of September 19th. Curb and sidewalk removal as well as replacement will begin the week of September 26th. Milling is expected to begin the week of October 13th.
We appreciate your patience and understanding while we complete these necessary improvements to our downtown infrastructure.
**All work is weather permitting with the possibility of delay.
UPDATE 9/7/2022:
The Village’s street improvement program is underway. Two components of the project currently in progress are:
- Concrete removal and repairs throughout the project area. The contractor is starting curb replacement on Slocum Lake Rd and Brown St. The work on Slocum Lake Rd will require traffic entering and exiting the Country Ridge subdivision to be detoured to Brown St for five to seven days. The entrance will reopen during the week of September 12.
- Asphalt grinding on Nancy Ct, Barbara Lane, Garland Rd, Van Buren Ave, Monroe Ave, Edgewater Parkway, Washington Ave, Jackson Ave. The existing asphalt will be removed to prepare for new layers.
Slocum Lake Rd and Brown Street Repairs Letter
7/5/2022 As part of the Village’s pavement preservation efforts, the Village Board has approved various streets to be included in the 2022 Street Improvement Project. The project will include pavement removal and replacement, pavement patching, sections of sidewalk, curb and gutter removal and replacement, thermoplastic striping, adjustment of structures and parkway restoration. The project will include roughly 3.75 roadway miles and should take approximately 15 weeks to complete. Construction will begin August 1st, with Main Street work beginning after September 21st.
UPDATE: For additional information on the Main Street portion of the Road Improvement Project, view the FAQ sheet (pdf).
2022 Street Improvement Project Scope:
Street Name |
Project Area |
Wilson Ave |
Main St – Ridge St |
Lake View Ave |
West End – Hammond St |
Ridge St |
Kimball Ave - Route 176 |
Ridge Ct |
Ridge St |
Lotus St |
High St – Kimball Ave |
Oaks Ave |
Barrington Rd - Main St |
High Ct |
All |
High St and Cul-de-Sac |
Lotus St – Alvina St |
Garland Rd |
Bonner Rd - South of Northshore Dr |
Nancy Ct |
All |
Barbara Ln |
Bonner Rd – Sheridan Dr |
Van Buren Ave |
Bonner Rd – Sheridan Dr |
Monroe Ave |
Bonner Rd – Sheridan Dr |
Alley (Edgewater Pkwy) |
Madison Ave – Jackson Ave |
Edgewater Pkwy |
Monroe Ave – Jackson Ave |
Washington Ave |
Bonner Rd – Northshore Dr |
Jackson Ave |
Bonner Rd – Sheridan Dr |
Jackson Ave |
North Shore Dr – Edgewater Pkwy |
Slocum Lake Rd |
Route 12 - Brown St |
Brown St |
Route 176 - Slocum Lake Rd |
Main St |
Garland Rd - Route 176 |
Sunset Ridge Intersection |
Intersection |
Woodland Rd |
North of Sunnyside Ave & South of Highland Ave |
Motorists are encouraged to slow down when driving through or near any road construction site and be alert for construction workers. Once the surface is removed and before the new layer of asphalt is applied, the street will have a rough surface. Drivers, cyclist and pedestrians should use caution, especially near protruding manhole covers.